What is not included in prevention costs?

a.

quality planning

b.

formal technical reviews

c.

test equipment

d.

equipment calibration and maintenance

Posted under Software Engineering

Answer: (d).equipment calibration and maintenance

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is not included in prevention costs?

Similar Questions

Discover Related MCQs

Q. Software quality assurance consists of the auditing and reporting functions of management.

Q. CMM stands for

Q. The ISO 9000 series of standards is a program that can be used for external quality assurance purposes.

Q. According to ISO 9001, the causes of nonconforming product should be

Q. .CO policy in CMM means

Q. ISO 9001 is not concerned with ____________ of quality records.

Q. Which of the following is not a maturity level in CMM?

Q. In CMM, the life cycle activities of requirements analysis, design, code, and test are described in

Q. Which of the following requires design control measures, such as holding and recording design reviews and qualification tests?

Q. The CMM emphasizes

Q. _______ states that, where appropriate, adequate statistical techniques are identified and used to verify the acceptability of process capability and product characteristics.

Q. Quality Management in software engineering is also known as

Q. Quality also can be looked at in terms of user satisfaction which includes

Q. Inspections and testing are what kinds of Quality Costs?

Q. According to Pareto’s principle, x% of defects can be traced to y% of all causes. What are the values of x and y?

Q. What is Six Sigma?

Q. Which of the following is not a core step of Six Sigma?

Q. Non-conformance to software requirements is known as

Q. Software safety is equivalent to software reliability.

Q. Misinterpretation of customer communication is a sample of possible cause defects.